There are two scheduling and filtering options available on the Import Task(s) dialog box. These options control the schedule of imported tasks and limit the number of items listed following the task import.
The check boxes are selected by default. To deselect the options, clear the check boxes.
Disable the schedule(s) of imported task(s): The imported task element schedules are disabled. This prevents an imported task from running before it is reviewed. To run an imported task, you must enable the task schedule. For more information, see Add/Edit Task Schedule.
Filter to display the imported task(s) only: The task list filter is modified to list only imported tasks. This limits the number of tasks listed, to make it easier to find the imported tasks. To change the listed tasks, modify. For more information, see Searching, Filtering and Sorting.